| Location of performance / Site: | Liebknechtstr. 71, Magdeburg, Saxony-Anhalt, Germany, Europe |
|---|---|
| Period: | Jul - Nov 2022 |
| Responsible company location: | BAUER Resources GmbH, Bereich Bauer Umwelt, Standort Roßwein |
Remediation of soil and groundwater through pre-excavation, large-hole drilling, groundwater purification and disposal.
| Pollutants: | Gasoline, diesel, heating oil (TPH), BTEX, CHC / HVOC |
|---|
| Provision of excavated material: | Direct loading |
|---|---|
| Conveyor flow exhaust air treatment: | 20000 m³/h |
| Water treatment: | Sedimentation basin, Activated carbon filter, Sand filter |
| Construction and demolition waste: | Construction and demolition waste without hazardous substances, Concrete (17.01.01), Soil and stones without dangerous substances, Soil and stones containing dangerous substances, Coal tar and tarry products (17.03.03), Soil and rocks under AVV 170504, other construction and demolition wastes containing dangerous substances |
|---|---|
| Transport: | Container, Gas-tight container, Saddle, Saddle planned, Truck |
| Tonnage: | 20000 to |
| Treatment methods: | Breaking / Sieving, Separating, Sieving, Washing, Landfill |
| Loading category: | Z 2 LAGA Soil, > Z 2 LAGA Soil, DK I, DK II |
| In-situ process: | Pump and Treat |
|---|---|
| Treatment methods: | Activated carbon filtration, Solids sedimentation, Gravel / Sand filtration |
| Other technical conditions: | Automatic filter backwash, Sludge storage, Control technology with remote access, Data storage online |
| Volume flow: | 10 m³/h |
| Dismantling amount: | Deep Debris Clearance |
|---|---|
| Dismantling process: | Stripping, Selective dismantling, Filling |
| Type of building: | Bunker, Industrial buildings |
| Equipment: | Excavator, Big rigs, Wheel loaders, Rolls |
|---|---|
| Earthworks: | Excavation, Road bed excavation, Building pit, Subgrade |
| Excavation method: | Conventional with loader and excavator, Replacement bores |
| Tonnage: | 20,000 t |
| Filling materials: | Concrete, Sand, Gravel |
| Fields of application: | Soil remediation |
| Methods: | Well keeping, Sump pit |
|---|---|
| Type of dewatering: | Open |
| Flow: | 10 m³/h |