Aerial view landfill remediation Bad Dürkheim Am Bruchhübel
| Location of performance / Site: | Am Bruchhübel, Bad Dürkheim, Rhineland-Palatinate, Germany, Europe |
|---|---|
| Period: | Apr - Sep 2008 |
| Responsible company location: | Schrobenhausen (Headquarters) |
| Project Partners: |
|---|
| Result: | Landfill Cover |
|---|
Deporting the existing sward
Loosening of the existing subsurface (30 cm)
Application of the water storage layer (1.70 m) and infiltration layer (0.30 m)
Surface driving with a tracked vehicle with a surface pressure of less than 1.5 t/m²
Installation quality “no compression” (no driving, no construction with standard machines, no intermediate storage)
high performance required: 100,000 m³ in 16 weeks
severe weather dependencies
| Surface sealing: | Excavation-damaged zone, Water balance layer, Water storage layer |
|---|---|
| Surface sealing area: | 44000 m² |
| Installation materials cubature: | 88000 m³ |
"Written confirmation"